Avonley Road, Phase 1

Client:

Bespoke Modular Developments Ltd

Location

New Cross

Our Role

Greenfield Demolition were awarded as sub-contractor to undertake the demolition works at the former MOT/Garage site in New Cross for our second project for Bespoke Modular Developments Ltd.

Scope

  • Asbestos Removal
  • Soft Strip (including separations)
  • Demolition (full)
  • Slab and Foundation Removal
  • Crush Arisings and Stockpile


Challenges

Our biggest challenge at New Cross was the close proximity to the surrounding neighbouring buildings. Each of the four buildings, three of which were removed in phase 1, had to be carefully demolished/dismantled on the boundary walls. This took one of our most experienced teams to complete within three weeks ahead of program.

Phase two is set to commence late 2018 which will bring a more complex method of demolition with the building being structurally weak.