The Orchards Shopping Centre, Haywards Heath
Overview:
Greenfield Demolition was awarded the strip out and alterations contract by RB Construction for Unit 20 & 21 The Orchard Shopping Centre where the two units will be merged into one.
This is the third contract completed for R&B Construction Group
Our Scope:
- Carry out the soft strip
- Partial Removal of wall
- Remove part of the existing load bearing wall
- Form openings
- Saw cut the existing slab
- Break out remainder of load bearing wall
Project Review
Client: | RB Construction |
Location: | Hayward Heath, West Sussex |
Start: | September 2016 |
Finish: | September 2016 |
Program: | 2 weeks |