Chequers Hotel
Overview
Client: Ashurst Construction
Location: Horley, Surrey
Greenfield Demolition were awarded the demolition works at Chequers Hotel by Ashurst Construction to demolish three buildings within the hotel boundary.
Our Scope:
- Strip Out
- Roof Removal
- Separations
- Demolition
- Slabs and Foundation Removal
- Clear Arising from Site
Challenges
Our main challenge was overgrown vegetation on this site. The roof had to be removed by hand using complex methods because of a tree branch growing through the building. The site had been standing for about a decade before the development had started.
Works were successfully completed within program. Ashurst Construction also instructed us to carry on on site to undertake the Groundwork package.